Plastering New Office

Multi-trade Property Improvements plastering projects of a new office in Rhu

Plaster works in an external office in Rhu.
The full job took 12 hours to complete.
Place floor protection in the full area.
Fibre tape to joints and internal corners.
Fit thin coat beads to all external corners (window and door in goes).
Plaster skim to ceiling and walls.
Cleaned the work area and dispose of all waste materials.
3 / 4 days drying out, and the ceiling is ready for painting.

Plastering New Office
ASK US FOR A FREE QUOTE ON ALL PROPERTY WORK